Step
1 - Preparation joining NGOs with Asian experience of rural
communities water management and European
OSIRIS
partners, workshops with Asian national and provincial authorities
and regional organisations about the outputs of the European OSIRIS
programme and their possible adaptation, choice of local authorities/communities
for case studies in the most disaster-prone floodplains (Cambodia:
Prey Veng prov, Lao PDR: Champasak
prov, Vietnam: Hai Duong prov).
Step
2 - On-the-field surveys in the selected local communities to
gather information about the communities' experience and practices
in water management and floods, what improvements they would suggest
to meet their needs and to help them getting involved in the decision-making
process.
Step
3 - After selecting one community per country, partners will
co-operate with the relevant institutions in the 3 countries in
developing and adapting specific ITC tools in order to meet the
needs of these pilot communities and definition of the test validation
methodology, with European and Asian professionals, including transfer
of technology to local institutes.
Step
4 - Testing and evaluation with the participation of these
communities and experts from independent NGOs, reporting and further
evaluation with the different levels of local authorities and the
relevant national and regional organisations, particularly the Mekong
River Commission Secretariat (Vientiane) in order to
prepare recommendations to be presented during the Final Seminar
and published in the web site.
Milestones
Month
5 : workshops in Phnom Penh, Vientiane and Hanoi with MRC and National
authorities
Month
15-20 : reporting field surveys to national authorities in Vientiane,
Phnom Penh, Hanoi and strategic orientations definition for ITC
tools development.
Month
27 : A workshop in Hanoi to validate a prototype and prepare recommendations to adapt it to diferente pilote sites.
Month
28-29 : Field missions to adapt the tool to the appointed pilote sites, users training.
Month
30 : final reporting
Month
31 : final seminar in Vientiane with the MRC Secretariat
France
CETMEF
Gilles Morel – Project manager
2, Bd Gambetta
BP60039
60321 Compiègne Cedex
Tél.
33 (0) 3 44 92 60 49
Fax : 33 (0) 3 44 92 60 70
ISTED
Agnès
Huchon
Task Manager
La Grande Arche, Paroi Nord
92055 La Défense Cedex
Tél. 33 (0) 1 40 81 78 05
Fax :33( 0) 1 40 81 26 76
Mél.
: agnes.huchon@i-carre.net
|
 |
|
Vietnam
Vietnam
Water Partnership CWE
() Jean Brunot de Rouvre, Project manager
Eric Castelli, director and
Sébastien Desprès, Task Manager
MICA
Université de Technologie d'Hanoi
1Dai Co viet st, Hai Ba Trung, Hanoi, Vietnam
Tél.
84 4 868 30 87
Fax :
84 4 868 3551
Mél. : sebastien.despres@gmail.com
|
|